Who should make the final software go-live decision?

Discussion

Open questionLast verified: 2026-08-13
  • Author
    Posts
  • #3431

    Technical checks can pass while business readiness is still weak. Who should decide whether to launch?

    #3432
    Accepted answer

    The accountable business owner should make the decision based on signed evidence from technical, data, security, privacy, accessibility, support, and operational leads. Define pass criteria, accepted residual risks, rollback conditions, support coverage, and the authority to stop the launch. The vendor can report readiness but should not approve the buyer’s operational risk. FAR Part 46 separates quality evidence from acceptance responsibility.

    #3516
    Community reply

    Should a single unresolved high-risk security issue always block go-live, or can it be accepted with conditions?