Discussion
Open questionLast verified: 2026-08-13
- AuthorPosts
- 17th August 2026 at 8:43 am #3411
A long shortlist creates more demos and scoring work, but a very short list can remove useful competition. What’s a practical approach?
17th August 2026 at 11:32 am #3412Accepted answerDo not choose a fixed number before doing market research. First define the need and minimum eligibility, then keep every credible supplier that can meet it within the procurement method and evaluation capacity. A shortlist is defensible when exclusions use published criteria and the remaining field preserves meaningful comparison; convenience alone is not a sound reason for exclusion. FAR Part 10 lists market research methods for identifying capable sources.